Copel (CPLE3) will have capex (investment program) of R$21.1 billion for the 2027 to 2030 cycle, approved by the Board of Directors on November 18, 2026. Of the total, 67% goes to Copel Distribuição, 24% to generation assets, including the LRCAP expansion, 7% to transmission and 2% to the company's other projects.
The investments aim at growth through the expansion of the operating asset base, with emphasis on the expansion of the Governador Bento Munhoz da Rocha Neto (Foz do Areia) and Governador Ney Braga (Segredo) hydroelectric plants. The program also provides for continued initiatives to raise service quality and operational efficiency.
For 2027, planned capex is approximately R$5.5 billion, exactly R$5,454.9 million. Copel Distribuição will concentrate about R$2.9 billion (R$2,944.9 million), aimed at service quality and operational excellence.
Copel Geração e Transmissão will invest approximately R$2.4 billion (R$2,413.6 million). Of that amount, R$1,920.2 million goes to generation, with R$1,803.3 million in hydroelectric plants and R$116.9 million in wind power. Another R$403.7 million is earmarked for reinforcements and improvements in transmission and R$89.7 million for other projects.
The remaining R$96.4 million will support initiatives in the Commercialization, Services and Holding areas, including Copel's innovation plan and programs and other equity interests.